|
Hello - I'm about to embark on a major bathroom remodeling (i.e. gutting that part of the house). This is in a *single* bathroom house and so it's going to be a big disruption to our life for the period that the bathroom is not available for our use. The project is probably going to cost around $25000. I've seen and heard the horror stories of contractors who take forever to finish projects. So, applying good old capitalist principles, I want to make in the contractor's best interest to get it done quickly and on schedule. To that end, I'm willing to put up an extra pile of money (say, $3000) and then have a cluase that says that after a previously agreed-upon period of contruction during which we have no bathroom (i.e. 2 weeks), that pile gets smaller by $500 a day. Further, after that pile has been eaten a way (after 6 days, in this case), there *continues* to be a $500/day penalty against the final payment. Once we're able to use the bathroom ("use" being strictly defined), the bleeding stops. I'll be using a reputable contractor, registered with NARI/etc, but I still want something in writing that protects me or at least gives the contractor an obvious incentive to get it done, besides him just wanting to collect on the final 10% payment. Can someone point me to precedents for this? How can I word this clause best so that I get the incentive behavior I want but it's not so onerous (or weird) that nobody will accept the terms?
|
| |
| |
Use "liquidated damages" instead of penalty. Courts don't like penalties. But if 2 parties agree on a per day damage amount before signing a contract (that is known as "liquidated damages" they will enforce it.
|
| |
| |
Hello - I'm about to embark on a major bathroom remodeling (i.e. gutting that part of the house). This is in a *single* bathroom house and so it's going to be a big disruption to our life for the period that the bathroom is not available for our use. The project is probably going to cost around $25000. I've seen and heard the horror stories of contractors who take forever to finish projects. So, applying good old capitalist principles, I want to make in the contractor's best interest to get it done quickly and on schedule. To that end, I'm willing to put up an extra pile of money (say, $3000) and then have a cluase that says that after a previously agreed-upon period of contruction during which we have no bathroom (i.e. 2 weeks), that pile gets smaller by $500 a day. Further, after that pile has been eaten a way (after 6 days, in this case), there *continues* to be a $500/day penalty against the final payment. Once we're able to use the bathroom ("use" being strictly defined), the bleeding stops.
Illegal here in this state..IIRC.. HOWEVER, you CAN put in a clause that states a given amount, not to exceed XX per day will be subtracted from the final payment..
I'll be using a reputable contractor, registered with NARI/etc, but I still want something in writing that protects me or at least gives the contractor an obvious incentive to get it done, besides him just wanting to collect on the final 10% payment.
FINAL 10%????? Wow...your states got some nice contractor laws....here, by law, we are only allowed to get a deposit of 5%...and remainder upon completion..
Can someone point me to precedents for this? How can I word this clause best so that I get the incentive behavior I want but it's not so onerous (or weird) that nobody will accept the terms?
Trick is finding a contractor that lets YOU set the terms.... None here will...
|
| |
| |
Chris Campbell wrote:>>
Hello -
I'm about to embark on a major bathroom remodeling (i.e. gutting that part of the house). This is in a *single* bathroom house and so it's going to be a big disruption to our life for the period that the bathroom is not available for our use. The project is probably going to cost around $25000.
I've seen and heard the horror stories of contractors who take forever to finish projects. So, applying good old capitalist principles, I want to make in the contractor's best interest to get it done quickly and on schedule. To that end, I'm willing to put up an extra pile of money (say, $3000) and then have a cluase that says that after a previously agreed-upon period of contruction during which we have no bathroom (i.e. 2 weeks), that pile gets smaller by $500 a day. Further, after that pile has been eaten a way (after 6 days, in this case), there *continues* to be a $500/day penalty against the final payment. Once we're able to use the bathroom ("use" being strictly defined), the bleeding stops.
I'll be using a reputable contractor, registered with NARI/etc, but I still want something in writing that protects me or at least gives the contractor an obvious incentive to get it done, besides him just wanting to collect on the final 10% payment.
Can someone point me to precedents for this? How can I word this clause best so that I get the incentive behavior I want but it's not so onerous (or weird) that nobody will accept the terms?
That's done on a fairly routine basis. But in your case, you should lower the "fine" to a $100 a day. At 500 a day, that's gonna show you being paid by the contractor in short order. If the contractor has quite a bit of experience in this area, he'll understand what your needs are. A bathroom makeover should not take two weeks. After all, a team of five people can completely remodel a house in 5 days, and we're only talking of a bathroom here. Unless your bathroom is ten times the size of a standard one.
|
| |
| |
The contractor will generally have a standard form of contract and it will usually make provision for liquidated damages - with a daily amount to be included. You need to find that provision and negotiate on the rate.
|
| |
| |
Chris Campbell wrote:
Hello - I'm about to embark on a major bathroom remodeling (i.e. gutting that part of the house). This is in a *single* bathroom house and so it's going to be a big disruption to our life for the period that the bathroom is not available for our use. The project is probably going to cost around $25000. I've seen and heard the horror stories of contractors who take forever to finish projects. So, applying good old capitalist principles, I want to make in the contractor's best interest to get it done quickly and on schedule. To that end, I'm willing to put up an extra pile of money (say, $3000) and then have a cluase that says that after a previously agreed-upon period of contruction during which we have no bathroom (i.e. 2 weeks), that pile gets smaller by $500 a day. Further, after that pile has been eaten a way (after 6 days, in this case), there *continues* to be a $500/day penalty against the final payment. Once we're able to use the bathroom ("use" being strictly defined), the bleeding stops. I'll be using a reputable contractor, registered with NARI/etc, but I still want something in writing that protects me or at least gives the contractor an obvious incentive to get it done, besides him just wanting to collect on the final 10% payment. Can someone point me to precedents for this? How can I word this clause best so that I get the incentive behavior I want but it's not so onerous (or weird) that nobody will accept the terms?
go to a local lender that does alot of home building loans.. they gonna be the ones that have the contracts written up with no loop holes.. i know 30 yrs. ago when i had my home built and borrowed money from them for the project, they had the builder(general contractor) by the balls and had everything covered.. it was $100 a day at that time, dont know what it would be nowdays... but i am sure they have some blank contracts that you can look at or get some advice.. let them think that you going to them to borrow money, but you are not sure how much or what and see what they say????? hope this helps...
|
| |
| |
What are you talking about ?
The contractor will generally have a standard form of contract and it will usually make provision for liquidated damages - with a daily amount to be included. You need to find that provision and negotiate on the rate.
|
| |
| |
Hello - I'm about to embark on a major bathroom remodeling (i.e.
gutting that
part of the house). This is in a *single* bathroom house
and so it's
going to be a big disruption to our life for the period
that the
bathroom is not available for our use. The project is
probably going
to cost around $25000. I've seen and heard the horror stories of contractors who
take forever
to finish projects. So, applying good old capitalist
principles, I
want to make in the contractor's best interest to get it
done quickly
and on schedule. To that end, I'm willing to put up an
extra pile of
money (say, $3000) and then have a cluase that says that
after a
previously agreed-upon period of contruction during which
we have no
bathroom (i.e. 2 weeks), that pile gets smaller by $500 a
day.
Further, after that pile has been eaten a way (after 6
days, in this
case), there *continues* to be a $500/day penalty against
the final
payment. Once we're able to use the bathroom ("use" being
strictly
defined), the bleeding stops. I'll be using a reputable contractor, registered with
NARI/etc, but I
still want something in writing that protects me or at
least gives the
contractor an obvious incentive to get it done, besides
him just
wanting to collect on the final 10% payment. Can someone point me to precedents for this? How can I
word this
clause best so that I get the incentive behavior I want
but it's not
so onerous (or weird) that nobody will accept the terms?
$500 a day might be a bit steep, but it is your inconvenience to measure as it is your house and your deprivation of use. The biggest problem often attendant to delay penalties is their not being equitable or a balance between contract considerations. You have described a penalty that does in a sense reward the contractor for timely performance but you have stated it in a manner that does not explicitly state a reward for timely performance. I know, you have the money on the table, but once signed on the line, nearly anyone would consider that the contract price. Period. A good penalty clause contract has penalty offsetting reward terms. If deprivation of your bathroom is worth $500 a day to you, then use must also be worth $500 a day to you. (Not likely, which is why I said I thought it a bit high on a $25,000 contract.) If so, then the logical argument is that finishing a day early is worth an extra $500 to the contractor. Right? Most government contracts, as example, have monitored schedules, adjusted for conditions as the work progresses, wherein the contractor pays a penalty for "unearned" delay and gains a bonus for "earned" early delivery. For your stick, you should have an equal carrot. Also, remember, you must monitor the progress. You must allow for certain delays (historically, far more likely caused by the homeowner than the contractor) and, less frequently, the contractor must allow for some opportunities to shorten the reasonable duration (the homeowner yields to a more available, necessary product choice). Now, on large government contracts, this is a worthwhile endeavor . . . from both perspectives, the government and the contractors. Monitoring the ongoing process is a significant investment to both parties, but the loss or gain is even more significant. I do not think your $25,000 bathroom is worth the effort. Not on your part and not on the contractor's part. You might select a contractor on a separate basis and then discuss your concerns with him. Reach a mutually acceptable agreement (in writing) at that time. Do not include such a provision in your "Invitation to Bid." You will prevent the better contractors from being at all interested in the headache (including you, for that matter), and some less worthy contractor may well see an opportunity to sucker you. Jim our
|
| |
| |
I'm about to embark on a major bathroom remodeling (i.e. gutting that part of the house). This is in a *single* bathroom house and so it's going to be a big disruption to our life for the period that the bathroom is not available for our use. The project is probably going to cost around $25000.
Doesn't anyone else find it curious that someone is going to spend $25,000 to remodel the bath of a house with only one bath? Does this make sense? Sounds pretty stupid to me. I smell a troll when (among other things) I see the following: 1) Questions involving implausible situations. 2) The OP's lack of participation after first post.
|
| |
| |
The contractor will generally have a standard form of contract and it will usually make provision for liquidated damages - with a daily amount to be included. You need to find that provision and negotiate on the rate.
A standard contract that volunteers liquidated damages? hehehehe That's a good one! Ever consider stand up?
|
| |
| |
Hello - I'm about to embark on a major bathroom remodeling (i.e. gutting that part of the house). This is in a *single* bathroom house and so it's going to be a big disruption to our life for the period that the bathroom is not available for our use. The project is probably going to cost around $25000. I've seen and heard the horror stories of contractors who take forever to finish projects. So, applying good old capitalist principles, I want to make in the contractor's best interest to get it done quickly and on schedule. To that end, I'm willing to put up an extra pile of money (say, $3000) and then have a cluase that says that after a previously agreed-upon period of contruction during which we have no bathroom (i.e. 2 weeks), that pile gets smaller by $500 a day. Further, after that pile has been eaten a way (after 6 days, in this case), there *continues* to be a $500/day penalty against the final payment. Once we're able to use the bathroom ("use" being strictly defined), the bleeding stops. I'll be using a reputable contractor, registered with NARI/etc, but I still want something in writing that protects me or at least gives the contractor an obvious incentive to get it done, besides him just wanting to collect on the final 10% payment. Can someone point me to precedents for this? How can I word this clause best so that I get the incentive behavior I want but it's not so onerous (or weird) that nobody will accept the terms?
Liquidated damages for delays are common on large projects and providing an early completion incentive prevents a purely adverserial relationship before the contract is signed. A good idea, I think, is to ask for a detail schedule so you can follow along and help the schedule where you can. The issue you will probably run into are owner caused delays. It may not take much for the contractor to claim a day lost was your fault, therefore he gets an extra day. Some possible causes of these delays could be any owner furnished material being late, any late selection of finishes, any finishes requiring special order, any finishes no longer available and needing reselection, any lead time for special orders, etc. These items should appear on the schedule and be accounted for except those that are truly outside of the contractor's control. Similarly, you should factor in the permit and inspection process. The schedule should account for inspections and if you pulled the permit, this could be your delay. Sincerely, Donald L. Phillips, Jr., P.E. Worthington Engineering, Inc. 145 Greenglade Avenue Worthington, OH 43085-2264 dphillips@worthingtonNSengineering.com (remove NS to use the address) 614.937.0463 voice 208.975.1011 fax http://worthingtonengineering.com
|
| |
| |
In article <c31fa7b1.0308041424.71119183@posting.google.com>, Christopher Green <cj.green@worldnet.att.net> wrote: OP's interest in a penalty clause of $500/day is counterproductive. No contractor worth hiring would agree to it, and the others would never have the resources to pay it when they flaked out -- at which point OP would find out that they were judgment-proof and the subs and vendors were filing mechanic's liens. We agree. The clause would eliminate the very contractors he wants to hire. -- Lyle B. Harwood, President Phoenix Homes, Inc. (206) 523-9500 www.phoenixhomesinc.com
|
| |
| |
You are really full of it.... I would not even take my skill saw to a job where I am the "one to be hanged" before the job even starts.... What one must do is to find a reputable and professional contractor and work with them to produce the desired result. This adversary BS from the getgo is going to run off any reputable high level contractors.... holding back 50% of the job..... you're nuts.... Jim Fincher
Penalty clauses and liquidated damages clauses have some problems. First, the clause has to be drafted carefully so that the court interprets the clause as a liquidated damages clause rather than a penalty. That means make sure a local attorney experienced in construction matters drafts it or reviews it, and advises on the amount. Second, if you have a liquidated damages clause, that's all you get if there is a breach involving failure to complete on time. It may be less than you would get in actual damages. Third, it might be difficult to find a contractor who wants the job badly enough to sign up for liquidated damages. The second most important thing you can do is revise the payment schedule so that 50% of the price is not paid until completion. 10% is a proper amount if there are progress payments tied to actual progress. A retainage that small is ok if there is an architect reviewing the percentage of completion with every progress payment request. 10% is not the appropriate amount of retainage in a bathroom remodeling contract. If you can't get the builder to accept 50%, you could go down to 40%, I suppose, but if the builder insists on 10%, find a new builder. The most important thing you can do is insist on a performance bond. The price of the bond will be added to the contract price, but it's worth it. If the contractor doesn't do the job on time, write a letter terminating the contract for breach, hire another contractor to finish, file a claim against the bond. The bonding company will go after the contractor for reimbursement. The bond will provide plenty of incentive. If you have any trouble negotiating a contract with a performance bond and a high retainage, the easiest way to handle it is to borrow the money from a bank. Use the bank's rules about contract format. Experienced, reputable builders will have no objection to either of the clauses you want, and will be accustomed to bank rules. You can reduce the interest expense by repaying the bank early. McGyver
|
| |
| |
Some very good points here Jim.... the OP's entire posting makes this GC shudder as to what one would be getting into with a contract to build that bath.... what most of these owners forget is that the entire building process should be a partnership between the owner and builder... this person's approach certainly casts it differently... Jim Fincher
gutting that and so it's that the probably going take forever principles, I done quickly extra pile of after a we have no day. days, in this the final strictly NARI/etc, but I least gives the him just word this but it's not $500 a day might be a bit steep, but it is your inconvenience to measure as it is your house and your deprivation of use. The biggest problem often attendant to delay penalties is their not being equitable or a balance between contract considerations. You have described a penalty that does in a sense reward the contractor for timely performance but you have stated it in a manner that does not explicitly state a reward for timely performance. I know, you have the money on the table, but once signed on the line, nearly anyone would consider that the contract price. Period. A good penalty clause contract has penalty offsetting reward terms. If deprivation of your bathroom is worth $500 a day to you, then use must also be worth $500 a day to you. (Not likely, which is why I said I thought it a bit high on a $25,000 contract.) If so, then the logical argument is that finishing a day early is worth an extra $500 to the contractor. Right? Most government contracts, as example, have monitored schedules, adjusted for conditions as the work progresses, wherein the contractor pays a penalty for "unearned" delay and gains a bonus for "earned" early delivery. For your stick, you should have an equal carrot. Also, remember, you must monitor the progress. You must allow for certain delays (historically, far more likely caused by the homeowner than the contractor) and, less frequently, the contractor must allow for some opportunities to shorten the reasonable duration (the homeowner yields to a more available, necessary product choice). Now, on large government contracts, this is a worthwhile endeavor . . . from both perspectives, the government and the contractors. Monitoring the ongoing process is a significant investment to both parties, but the loss or gain is even more significant. I do not think your $25,000 bathroom is worth the effort. Not on your part and not on the contractor's part. You might select a contractor on a separate basis and then discuss your concerns with him. Reach a mutually acceptable agreement (in writing) at that time. Do not include such a provision in your "Invitation to Bid." You will prevent the better contractors from being at all interested in the headache (including you, for that matter), and some less worthy contractor may well see an opportunity to sucker you. Jim our
|
| |
| |
On Long Island there are 50 year old houses with one bath that are worth $300k to people who live and work there. $25k to fix one is nothing. Might take $50k or more.
The point is, if you're going to sink that much into a bath wouldn't it be a higher priority to add a 2nd bath? BTW, putting 25k into the only bath of a house worth 300k doesn't sound rational to me.
$25,000 sense?
|
| |
| |
OP's interest in a penalty clause of $500/day is counterproductive. No contractor worth hiring would agree to it, and the others would never have the resources to pay it when they flaked out -- at which point OP would find out that they were judgment-proof and the subs and vendors were filing mechanic's liens.
I agree. He mentioned sweetening the deal with an extra $3K to make it happen. Besides the fact that dumping an extra 12% into the deal also raises the troll red flags, it would be much more productive to find a way to have temporary facilities during construction -- or go to a motel for a week or two.
|
| |
| |
I'm just posting to thank you all for the excellent responses, remarkably free of the "you're an idiot!" posts one often gets on Usenet these days. I will take all of this advice under consideration, and I do plan to get review by a lawyer when it comes down to the final contract. Thanks again.
|
| |
| |
The point is, if you're going to sink that much into a bath wouldn't
it be a
higher priority to add a 2nd bath?
What if the only bathroom just happens to be 300 square feet??? : )
BTW, putting 25k into the only bath of a house worth 300k doesn't
sound
rational to me.
I have 2 1/2 baths in my home (and a rough in for when I like in the basement). I'd REALLY rather 1 1/2 baths with a HUGE main bath.
|
| |
| |
On 4 Aug 2003 17:22:53 -0700, chris-google@pobox.com (Chris Campbell) wrote:
I'm just posting to thank you all for the excellent responses, remarkably free of the "you're an idiot!" posts one often gets on Usenet these days. I will take all of this advice under consideration, and I do plan to get review by a lawyer when it comes down to the final contract. Thanks again.
Oh my! Just read this whole thread. Gets sillier and sillier. Liquidated damages, performance incentives, performance bonds , yada yada, yada. By the time your lawyer talks to my lawyer ... the damn bathroom could have been finished. Get serious! You're remodelling a bathroom, not building an airport. Pick a contractor you like, talk with the owners of the last two bathrooms he's done... and make your decision. Doesn't matter whether it costs five thousand, 25 thousand or 100 thousand ... it's a bathroom. Contractors are people ... they know they're taking your only bathroom out of service ... and they'll bend themselves out of shape to move the job along. If you have so little faith in the contractor (and in your own ability to judge people), why are you hiring him/her? Ken
|
| |
| |
On 4 Aug 2003 17:22:53 -0700, chris-google@pobox.com
(Chris Campbell)
wrote: Oh my! Just read this whole thread. Gets sillier and
sillier.
Liquidated damages, performance incentives, performance
bonds , yada
yada, yada. By the time your lawyer talks to my lawyer
.... the
damn bathroom could have been finished. Get serious! You're remodelling a bathroom, not
building an
airport. Pick a contractor you like, talk with the
owners of the
last two bathrooms he's done... and make your decision. Doesn't matter whether it costs five thousand, 25
thousand or 100
thousand ... it's a bathroom. Contractors are people ... they know they're taking your
only bathroom
out of service ... and they'll bend themselves out of
shape to move
the job along. If you have so little faith in the contractor (and in your
own ability
to judge people), why are you hiring him/her? Ken
Although I don't agree that the thread is silly, I do agree with the premise of this response. For the OP's peace of mind (and there are lots of folks out there who have a great mistrust of anything and everything, so they must live with that . . . thankfully, most of us do not), he should run the agreement by his attorney. He might also string have his attorney point out any areas of likely misinterpretation or needless liability on his part . . . listing them or margin=noting them. Then, he should discuss this with his builder. If that gets into a contest, he likely will be looking for another builder. If his attorney insists on rewriting the agreement, he is assured of looking for another builder . . . likely for a long, long time . . . or else find a very hungry builder, which would be a catastrophe for both parties. An attorney or an accountant looking over a contract for a party is being paid. He wants to do something for his pay. Keep that in mind. Also, a contract can not protect either party for every contingency. Keep that in mind. In a small project, a "small" agreement is likely best. Every lawyer will agree, a handshake is the very best contract. Unfortunately, they are not speaking literally. Jim
|
| |
| |
|